Under the Party Wall etc. Act 1996 you must give at least two months’ notice before work to an existing party wall, and at least one month before building a new wall at the boundary or excavating near a neighbour’s foundations. For a party structure or excavation notice, a neighbour who does not consent within 14 days is treated as dissenting. For example, a party structure notice handed over on 11 January 2027 allows a start from 11 March 2027.
How the dates are counted
The Party Wall etc. Act 1996 requires a building owner to tell adjoining owners before certain work. Which kind of notice you need sets the periods:
- Existing party wall or structure (work under section 2): a party structure notice, at least two months ahead.
- New wall on or at the boundary (section 1): at least one month ahead.
- Excavation near a neighbour (section 6): at least one month ahead.
Where the Act says a period begins with the day of service, that day counts as day one. So the 14 days for a notice served on the 11th end on the 24th. Where a month has no matching date, the page moves the earliest start to the next day so that the period is never cut short.
For post, the law treats service as happening when the letter would arrive in the ordinary course of post, unless the contrary is shown. This page allows 1 to 4 calendar days after posting as its own planning range. It uses the later date for the earliest start and the earlier date for the lapse. It does not count weekends or bank holidays separately.
Worked examples
Loft work on a party wall: notice handed over on 11 January 2027
The last day for consent is 24 January 2027, and from 25 January 2027 silence counts as dissent. A counter-notice is due by 10 February 2027. The notice period allows a start from 11 March 2027, and work must begin by 10 January 2028.
Foundations for an extension: excavation notice posted the same day
It counts as served 12 January 2027 to 15 January 2027 on the allowance here, so plan on a start no earlier than 15 February 2027.
Served at the end of January
A one month notice handed over on 31 January 2027 has no matching date in February, so the page shows 1 March 2027.
What changes the result
- The reply. Written consent can let the job go ahead on agreed terms. Dissent, real or deemed, sends the matter to one agreed surveyor or to a surveyor for each side. Their timetable is not fixed by the dates on this page.
- Counter-notices. For party structure work the neighbour can ask for extra works for their convenience, which may need design changes.
- Unresponsive parties. The Act gives 10 day periods after a written request for appointing surveyors and for surveyors to act.
- More than one neighbour or owner. Each adjoining owner needs a notice, which can include leaseholders as well as the freeholder. Each has its own dates.
- Defects in the notice. A notice missing required details or drawings may need to be served again, restarting the clock.
UK context and practical advice
The Act applies in England and Wales. It does not apply in Scotland or Northern Ireland, which handle shared walls differently. The GOV.UK guidance includes an explanatory booklet with template letters.
Talk to your neighbour before the formal notice arrives. Serve early, because the extra weeks are what absorb a dispute, but not so early that a party structure or excavation notice lapses before work can begin. Keep proof of the day and method of service. For anything structural, or if a dispute starts, speak to a party wall surveyor.
Assumptions and sources
| Rule used | Value | Source |
|---|---|---|
| New wall at the boundary | At least one month’s notice; consent within 14 days; no deemed dissent | Party Wall etc. Act 1996, section 1 (revised version as published; checked 25 November 2026) |
| Party structure notice | At least two months; lapses if work not begun within 12 months beginning with service | Party Wall etc. Act 1996, section 3 (revised version as published; checked 25 November 2026) |
| Counter-notice | Within one month beginning with service of the party structure notice | Party Wall etc. Act 1996, section 4 (revised version as published; checked 25 November 2026) |
| Deemed dissent | No consent within 14 days beginning with service | Party Wall etc. Act 1996, section 5 (revised version as published; checked 25 November 2026); for excavations Party Wall etc. Act 1996, section 6 (revised version as published; checked 25 November 2026) |
| Excavation | At least one month; 3 m and 6 m tests; same 12 month lapse | Party Wall etc. Act 1996, section 6 (revised version as published; checked 25 November 2026) |
| Surveyors and 10 day periods | Described, not dated | Party Wall etc. Act 1996, section 10 (revised version as published; checked 25 November 2026) |
| How notices are served | Delivery, post, or agreed electronic means | Party Wall etc. Act 1996, section 15 (revised version as published; checked 25 November 2026) |
| Service by post | Deemed at ordinary delivery unless the contrary is proved | Interpretation Act 1978, section 7 (revised version as published; checked 25 November 2026) |
| Post allowance | 1 to 4 calendar days | This page’s own allowance, set 25 November 2026 |
| Scope | England and Wales | GOV.UK, Party Wall etc. Act 1996: guidance (guidance updated May 2016; applies to England and Wales; checked 25 November 2026) |
Common questions
How much notice do I have to give under the Party Wall Act?
At least two months before work to an existing party wall or other party structure, using a party structure notice. At least one month for a new wall on or at the boundary line, and at least one month before excavating where section 6 applies.
What happens if my neighbour does not reply?
For a party structure notice or an excavation notice, a neighbour who does not consent within 14 days beginning with the day of service is deemed to have dissented, and a dispute is deemed to have arisen. Silence is not consent. The new wall notice under section 1 has no deemed dissent rule: without consent, you may only build the wall wholly on your own land.
When does excavation need a notice?
Section 6 applies where you dig within 3 metres of a neighbour’s building or structure and go lower than the bottom of its foundations, and in some cases within 6 metres, where the work would cross a line drawn down at 45 degrees from the bottom of those foundations. Ask someone competent to check your drawings against it.
Can I start earlier if my neighbour agrees?
Neighbours can often agree matters between themselves. Get any agreement in writing and be clear what it covers. This calculator shows the statutory periods and does not decide what an agreement allows.
Can I serve a party wall notice by email?
Section 15 allows electronic service only if the recipient has said they are willing to receive documents that way and the notice goes to the electronic address they specified. Otherwise deliver it or post it as the section describes.
Does a party wall notice expire?
A party structure notice and an excavation notice cease to have effect if the work has not begun within 12 months beginning with the day of service, or is not carried on with due diligence. If a notice has lapsed you need to serve a new one.
Does the Act replace planning permission?
No. It deals with your relationship with adjoining owners. Planning permission, building regulations and any other consents are separate.
Related calculators
Page last checked 25 November 2026.